Technical Quarterly Update Q2’17
The main actions undertaken during that time include the following: 1- New Paris backbone infrastructure renewal with 3 main phases (RFP selection, POC and deployment): RFPs: 3 RFPs have been launched based on technical compliance and cost competitiveness with the following results: Dark fibers: the main goal was to rebuild a dual core backbone (Telehouse 2 and Interxion PAR5) with every edge PoP dual attached to the core. Five new dark fibers have been deployed with new providers (IELO-LIAZO and…